From Testing to a Replicable Shoreline Model
Before attempting restoration across the entire lakefront, LAIA's proposed approach begins with a controlled micro-pilot project. The project is designed to test environmental conditions, restoration techniques, community processes, monitoring systems, and funding structures on a smaller scale before expanding.

Project Timeline
SITE SCREENING
Q4 2026

Finalize testing protocols and sampling locations. Conduct bulk-density and salinity testing across candidate lakefront segments to identify areas where soil conditions and salinity levels may support vegetation or oyster structures.
CO-DESIGN
Q1 2027

Integrate testing results into project design. LAIA and Pontchartrain Conservancy collaborate on a salinity-zoned micro-pilot with Jefferson Parish Floodplain Management to develop a repeatable framework for future projects.
BUILD & MONITOR
Q2–Q3 2027

Begin installation in approved testing zones. Pontchartrain Conservancy would lead scientific monitoring while LAIA coordinates the community process and related documentation to ensure long-term ecological viability.
CREDIT & SCALE
Q4 2027

Document applicable CRS activities and develop a replication blueprint for additional shoreline segments. Finalize CRS-related documentation and develop the next-stage scale-up plan to protect the lakefront for future generations.
Measuring Success
0.5 ft
Elevation Retention
Target: At least 0.5 feet above NAVD88. Purpose: Evaluate platform stability and soil integrity.
80%
Vegetative Coverage
Target: At least 80% survival. Purpose: Evaluate ecological viability of mid-salinity planting strategies.
+120 pts
CRS Credit
Planning target: +120 points. Potential activities: 420, 450, 510, and 540.
6+
Community Engagement
Target: At least 6 outreach actions. Examples: Public meetings, community education, and property-owner communications.
2+
Scientific Monitoring
Target: Two peer-reviewed submissions. Purpose: Validate ecological data and project outcomes.